Improve breed chain logic for when does don't take
I palpate my does to see if they took around 2 weeks. If a doe doesn't take, I rebreed her then. My issue is when I've considered a doe "bred" but she didn't take, then the "pregnancy check" was performed but the outcome is that the whole breeder task chain needs to restart. The only way I have to do this is to manually delete individual tasks in the current chain and reschedule the breeding to the current day. Is there a smarter way to do this?
Comments: 1
-
27 Jun, '22
Everbreed Admin AdminNow, when completing a pregnancy check, if you mark the pregnancy as "Missed", you'll get an option to have Everbreed automatically delete the rest of the tasks in the breed plan for you. You can then proceed to schedule a new breeding at your convenience.